Feasibility study on the Okavango river to Grootfontein link of the Eastern National Water Carrier, Volume 1 - Summary report

Contributor(s): Material type: TextTextLanguage: English Publication details: [Windhoek] : Water Transfer Consultants, 1997Description: [unnumbered pages] : illustrations; 29 cmSubject(s): DDC classification:
  • NAM 343.092 FEA
Summary: Water Transfer Consultants (W T C) was formed as a joint venture partnership between L C E, Bicon Namibia and Parkman Namibia, to undertake this Feasibility Study on the transfer of water from the Okavango River at Rundu to the Eastern National Water Carrier (canal) at Grootfontein. Undertaken for the Department of Water Affairs of the M A W F of the Government of Namibia, this Study initially updated the earlier Central Area Water Master Plan Study insofar as the historic water demands and water demand forecasts were concerdut. This lead to the determination of the water transfer requirements, and the preliminary design of a 250 km long, 700 mm diameter pipeline, to transfer 0.55 m3/s at 400 m static head, with four booster pump stations and river outlet works. A risk assessment and cost estimate were prepared, as well as financial and economic analyses on the preliminary design. An environmental assessment was also carried out to determine the impact of the proposed pipeline as well as the impact on the Okavango River and Delta, resulting from the proposed abstraction of water at Rundu. This study was concluded with the publication of a report in 6 volumes in August 1997.
Tags from this library: No tags from this library for this title.
Star ratings
    Average rating: 0.0 (0 votes)
Holdings
Item type Current library Call number Status Date due Barcode
Books Books Namibia Scientific Society Library Not for loan

Water Transfer Consultants (W T C) was formed as a joint venture partnership between L C E, Bicon Namibia and Parkman Namibia, to undertake this Feasibility Study on the transfer of water from the Okavango River at Rundu to the Eastern National Water Carrier (canal) at Grootfontein. Undertaken for the Department of Water Affairs of the M A W F of the Government of Namibia, this Study initially updated the earlier Central Area Water Master Plan Study insofar as the historic water demands and water demand forecasts were concerdut. This lead to the determination of the water transfer requirements, and the preliminary design of a 250 km long, 700 mm diameter pipeline, to transfer 0.55 m3/s at 400 m static head, with four booster pump stations and river outlet works. A risk assessment and cost estimate were prepared, as well as financial and economic analyses on the preliminary design. An environmental assessment was also carried out to determine the impact of the proposed pipeline as well as the impact on the Okavango River and Delta, resulting from the proposed abstraction of water at Rundu. This study was concluded with the publication of a report in 6 volumes in August 1997.

Jürgen Kirchner , Prof. W017998